| |
“The best-laid schemes of
mice and men Often go awry, And leave us nothing
but grief and pain, Instead of promised joy!*
The 18th century
poet, Robert Burns, got it right when he wrote
that well-meant plans will often change.
And
your project report may need to display those
changes against the original plan.
|
|
So, how can you show both
the baseline plan and the current plan in a single
report?
The best practice is to show both the baseline
and current data wherever possible, including:
-
Start and end dates
-
Milestone dates
-
Cost and spending
-
Man hours
-
Duration
|
|
Below is an example of this in
action, including:
-
Baseline and current task timelines, one on
top of the other
-
Graphs of current and baseline costs as
quarterly and cumulative values
-
Baseline and current start and finish dates
|