How
to Outline |
|
| Set-up
the column for outline indentation |
|
|
1. |
Click the
column heading the toolbar changes to the Selection tab
Current Object: Column Heading. |
 |
|
|
2. |
Click Switch to
Column. |
|
|
3. |
In the Column Type
and Format section, under Indent per Outline Level:enter a value
(such as 0.3) press the apply button . |
| |
|
| Set the
Tab key as the outlining shortcut |
|
|
1. |
Select Tools tab.
|
 |
|
|
2. |
In the Program Options section
choose Edit. |
|
|
3. |
Check Use the TAB key for outlining. |
|
|
NOTE: The
green arrow
can also be used to outline tasks. |
|
|
|
|
| Indent/Outline
a single task |
|
|
1. |
Click once on a task name.
|
|
|
2. |
Hit
the Tab key or click the right-facing green arrow icon on the
Toolbar. |
|
|
|
|
| Indent/Outline
multiple tasks at once |
|
|
1. |
Click once on a task name.
|
|
|
2. |
Hold
down the Ctrl key. |
|
|
3. |
Click once on
all other task names to be indented/outlined. |
|
|
4. |
Hit
the Tab key or click the right-facing green arrow icon on the
Toolbar. |
|
|
|
Back to top |
 |
|
| |
|
|
Organizing
with SmartColumns |
| Create
Outline Level, WBS Number, and TaskNumber SmartColumns |
| 1. |
Choose
the Insert tab. |
| 2. |
In the Rows, Column
section choose New Column. |
| 3. |
Choose from the list
of available columns. |
|
 |
|
|
|
|
Back to top |
 |
|
|
|
|
|
Choosing summary bar symbology |
|
|
1. |
Choose Format | Summary Bar Settings. |
|
|
2. |
Choose
symbols and a connector to display on all summary bar levels. |
|
|
|
|
|
| The symbols and
connectors in the drop-down lists show what is available in the
Toolbox. Thus, if the symbols and connector you want are not
available, then you'll need to first add them to the Toolbox. |
 |
|
|
|
|
|
|
For baseline summary, choose Format
| Baseline Setup
to choose task and summary level symbology
for baseline dates. |
|
|
|
Back to top |
 |
|
|
|
|
|
|
|
Collapsing
to summary level, or expanding to detailed task level |
|
|
|
|
| View
Summary Bars for upper level tasks |
|
|
1. |
Choose Format | Summary Bar Settings. |
|
|
2. |
Under When
to Draw,
check Always to display summary bars
at all times. |
|
|
|
|
| Show
Collapse/Expand Indictors |
|
|
1. |
Choose
View | Collapse/Expand Indicators. |
|
|
2. |
Use the
collapse/expand indicators to roll-up or drill-down outlined tasks. |
| |
| Roll-up
a single task line without Collapse/Expand Indictors |
|
|
1. |
Right-click
the task line to roll-up. |
|
|
2. |
Choose
Collapse Selected Task Line. |
|
|
**works
the same to Expand |
|
|
|
|
| Roll-up all tasks to a
certain outline level
without Collapse/Expand Indictors |
|
|
1. |
Right-click
a task line to roll-up to. |
|
|
|
For
example, if you want to roll-up all task lines to Level
1, right-click any Level 1 task. |
|
|
2. |
Choose
Collapse All Tasks to Selected Level. |
|
|
|
|
|
|
|
Back to top |
 |
|