| |
BUZZWORD |
|
MEANING |
| |
Actual
Cost (AC) |
|
The costs
actually incurred in performing the planned work. |
| |
Actual Cost of Work
Performed (ACWP) |
|
Previous
term for Actual Cost
(AC). |
| |
ANSI/EIA 748 Standard |
|
The
official standard of accepted criteria for EVM. These 32 criteria
replaced the original 35 criteria in the C/SCSC |
| |
Budget
At Completion (BAC) |
|
The total
of all budgets allocated to a project. |
| |
Budget |
|
A fiscal
plan of operations for a given time period. |
| |
Budgeted Cost of Work
Performed (BCWP) |
|
Previous
term for Earned Value (EV). |
| |
Budgeted Cost of Work
Scheduled (BCWS) |
|
Previous
term for Planned Value (PV) |
| |
Cost/Schedule
Control System Criteria (C/SCSC) |
|
Since 1967, these
35 criteria have been used
to ensure the government that contracts are managed properly. In
December of 1996, these 35 standards were superseded by 32 Earned Value
Management standards. |
| |
Cost Performance Index
(CPI) |
|
Cost
variance related as a ratio instead of a dollar amount. A ratio
less than 1 indicates that the value of the work that has been
accomplished is less than the amount of money spent.
CPI = (EV / AC). |
| |
Cost
Variance (CV) |
|
The
difference between the work that has been accomplished (in dollars) and
how much was spent to accomplish it. CV = (EV - AC). |
| |
Earned
Value (EV) |
|
The actual measured performance; the value of the completed work. EV
= (Budget x %Complete) for a given task or project. |
| |
Estimate
at Completion (EAC) |
|
A forecast
of total costs that will be accrued by project completion, based on past
cost performance trends. |
| |
Gantt
Chart |
|
A common
way of showing tasks over time. |
| |
Milestone |
|
An
important event. |
| |
Percent Complete |
|
Physical
progress as of the current date, related as a percentage of the task's
duration. For summary tasks, Percent Complete = (EV / Budget). |
| |
Planned Value (PV) |
|
The sum
total of the budgets for the planned work scheduled to be done within a
specified time. |
| |
Schedule Performance Index
(SPI) |
|
Schedule Variance related as a ratio instead of a dollar
amount. A ratio less than 1 indicates that work is being completed
slower than planned. SPI = (EV / PV). |
| |
Schedule Variance (SV) |
|
The
difference between what was planned to be completed and what has
actually been completed as of the current date. SV = (EV - PV). |
| |
Statement
of Work (SOW) |
|
A document
describing the work to be done on the contract. |
| |
To-Complete Performance
Index (TCPI) |
|
Indicates
the CPI that will be required throughout the remainder of the project in
order to stay within the stated budget. |
| |
Variance at Completion (VAC) |
|
The
difference between the new Estimate-at-Completion (EAC) and the original
Budget-at-Completion (BAC). |
| |
Work
Breakdown Structure (WBS) |
|
A
tree-like representation of the work to be done on a project. The
WBS graphically shows the division of work. |