Duration
SmartColumns
|
 |
|
|
|
This article refers to version 2006.
Click for Version 2008 |
| A Duration SmartColumn can be
used to show the amount of time worked. The time can be shown in minutes,
hours, days or weeks. |
| |
How to: Set up a
Duration SmartColumn
|
| Duration can easily be
added to any schedule. Here are the steps to go through to add a
Duration SmartColumn: |
| |
| 1 |
Insert a new column by choosing the Column
option on the Insert menu. |
| 2 |
Double-click the new column's heading. |
| 3 |
Click the SmartColumn Settings tab
and set the SmartColumn Definition to Duration |
|
 |
|
Milestones
Professional
takes into account a number of factors when computing the duration,
including:
|
|
The workday start and
end times. (The workday start and end times are set by clicking and
then clicking the Hourly/Minute tab). |
|
|
Whether or not you have
hourly detail turned on. |
|
|
Whether or not Saturdays
and Sundays are worked. |
|
|
Holidays that you might
have indicated. |
|
|
|
|
| |
Hourly detail
|
| A schedule can
have daily, hourly and even minute detail. Which level of detail is
used will affect the duration and other calculations. |
| |
| To turn hourly
detail on or off: |
| 1 |
Click the
toolbar icon. |
| 2 |
Choose the Hourly/Minute
tab. |
| 3 |
Click on or off the
Allow Hourly Detail option. |
|
| |
|
| |
Duration and the
single milestone
|
| |
| When hourly detail
is turned off, a single milestone will display a duration of 1 day: |
 |
| |
| When hourly detail
is turned on, a single milestone will display a duration of 0 days: |
 |
| |
|
| |
Duration and
multiple milestones
|
| In the example
below, hourly detail is off. With hourly detail off, the time span
includes all 4 days in the schedule: |
 |
|
| When hourly detail
is turned on, and the "Show Decimal Point on Duration and Percent
Complete" option is turned off, the durations on both tasks of this schedule
are 3
days. |
 |
|
| When hourly detail
is turned on, and the "Show Decimal Point on Duration and Percent
Complete" option is turned on, the duration on the second task is
more accurate: |
 |
| |
|
| |
Duration and Summary Bars
|
| |
| If your schedule is outlined,
summary bars can be used to display the overall duration. You can
choose to display the sum of the individual durations, or the overall
duration. The example below has the "Show Summary Duration in
Calendar Time" option turned on. |
| |
 |
| |
| The example below has the
"Show Summary Duration in Calendar Time" option turned on.
This option is set by choosing Options on the Tools menu and then choosing
the Proj. Man. tab. |
 |