KIDASA Software, Inc. Website   

HOME   |   BUY   |   DOWNLOAD   |  PRODUCTS   |    NEWS   |   SUPPORT   |   CONTACT   |   EXAMPLES   |   SEARCH

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

   

Calculation/Indicator SmartColumn options


Each Calculation/Indicator SmartColumn has two sections of Properties settings. The first is the calculation to-be-performed, and the second controls the optional graphical indicators. 

This article will refer to the calculations available on the "Calculations" tab one-by-one, while also referring throughout to the "Graphical Indicators" tab.  These and all other settings discussed below can be accessed by either inserting a new Calculation/Indicator SmartColumn, or by double-clicking the heading of an existing calculation column

 

Possibilities

 

 Make a calculation between two columns and show the resulting values

The most basic function of a Calculation/Indicator SmartColumn is to perform a simple arithmetic operation between two columns:

The two columns used can be Values SmartColumns, Duration SmartColumns, and either Baseline or Normal Date SmartColumns; however, both columns being used in the calculation need to be of the same type.  In the example below, the Values column "Cost" is being subtracted from the Values column "Budget." 

The column headed "Budget minus Cost" is the Calculation/Indicator SmartColumn which is simply displaying the results with no indicator symbols.


 

 

 Make a calculation between two columns and show results with symbols, text or colors

Continuing with the example above, you can add:

  • An indicator symbol with the numerical result                                   

On the Graphical Indicators tab, choose the current Calculation/Indicator SmartColumn as the "Column to compare."  This means the result of the calculation and the indicator symbol driven by that result will appear in the same column together.  In this case, the option "Display numerical value also" has been checked, and the indicator symbol will be aligned to the left:

 

 

 

The indicator conditions are chosen in the drop-down menu below the Column to compare settings.  To activate an indicator, select "Pick indicator symbology based upon the following conditions" and choose from the list:

First select your indicator symbol...

...then set the condition for that indicator to appear.  In this case, the green stoplight selected above will be displayed if the calculated value is greater than zero:

  • An indicator symbol only, without the numerical result:

On the Graphical Indicators tab, make sure to uncheck "Display numerical value also." Then, continue activating indicators as normal. 

In this example, we've checked the box "Fill cell with symbol color instead of drawing symbol," and added Indicator Text in lieu of displaying the calculated value:

...to get the following result:

    

 Convert the numerical result to a percentage and show a % Complete Indicator:

On the Graphical Indicators tab, you can check (or not) the "Display numerical value also" box.  Then, instead of selecting "Pick indicator symbology based upon the following conditions," select "Interpret value from compare column as a % and use the Percent symbol."

Then, the values driving the percentage should be either between 0 and 1 (i.e. 0.5, 0.75, etc) or whole numbers up to 100...

In the example below, the calculation between two Values SmartColumns - "Units Sold" divided by "Total Units" - results in the Calculation/Indicator SmartColumn "Item Sales." The results are being interpreted as percentages and then displayed with a % Complete Indicator...



Column times Percent Complete, Not Complete, or % of duration to current date

In addition to performing calculations between two columns, you can use a Calculation/Indicator SmartColumn to multiply a Values column by:

  • Percent Complete

In this instance, using a Budget column in the calculation will provide the Budgeted Cost of Work Performed, i.e. Earned Value (BCWP).

  • Percent Not Completed

Again, using the same Budget column, but in this case multiplying by Percent-not-completed, you can obtain the dollar value of the budgeted cost of remaining work.

  • % of Duration to Current Date

Finally, multiplying a Budget column by the % of Duration to the Current Date will give the dollar value of the Budgeted Cost of Work Scheduled, i.e. Planned Value (BCWS).


Indicator Only, based on the values in another column

It is frequently necessary to display just an indicator, which may be based on the value in a different column.  In that case, select "Indicator Only" in the Calculation Properties:

Then, in the Graphical Indicators section of the Calculation/Indicator SmartColumn Properties, select any Values column as the "Column to Compare."

In the first example below, the "Budget Minus Cost" calculation column is being used to drive the "Variance Indicator" column.  In the second example, a user-entered "Project Stage" Values SmartColumn is driving the indicator in the "Manager" column.  In this case, the indicator is simply filling the cells with a given color, while overlaying the text of the Manager's name:

              


Use a calculation result in another calculation

Using Calculation/Indicator SmartColumns, you can link a chain of two calculations together.  In the example below, the "Units (x) $ per Unit" is a calculation column multiplying "Units Sold" by a hidden "$ per Unit" column.  Then, a further calculation is being performed to determine the variance between the "Target Sales" column and the "Units (x) $ per Unit" Calculation SmartColumn.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  © Copyright KIDASA Software, Inc. 2008 All Rights Reserved   1114 Lost Creek Blvd., Suite 300 Austin, TX  78746  512-328-0167   sales@kidasa.com