XML Export


A Milestones file can be exported as an XML file. First, choose which Milestones columns should be exported, then save that data as an XML file.
 
Choose which Milestones columns to export to XML:
   
1 Under the File menu choose Export Data | XML | XML Column Mapping.
2 On the XML Export Preferences dialog box, choose <NAME> next to the column heading for the project activities. This is the only required field to export. Other critical data is exported by default (e.g. start and duration values for each activity)
3 Choose other fields next to any other Milestones columns you wish to export.
Export the selected data to an XML file:

1

Under the File menu choose Export Data | XML | Export Schedule to XML File.

2

Enter a File name and Save.
 
Notes:
When exporting Milestones information as an XML file and then importing that XML file into Microsoft Project, note that the many differences in functionality and default settings between Milestones Professional and Microsoft Project may cause some data to display differently in Microsoft Project. These differences include
but are not limited to:
  • Different holiday calendars, working/non-working weekends, workday start and end time, etc.

  • Microsoft Project uses resource tables, whereas Milestones can display user-entered resource names next to each activity. Accordingly, the exported XML file contains a placeholder resource name for each activity (e.g. MilestonesImportResource1, MilestonesImportResource2, etc.).

  • Microsoft Project uses a start or finish date and a duration value to create the Gantt bar. Different work day time periods, holiday calendars, working/non-working weekends can therefore result in a different finish date or start date compared to that in Milestones Professional.

Duration values are exported automatically. Duration is exported in hours, so it's important to set the working time period in the Milestones schedule.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 