Status Line

Show at-a-glance ahead/behind status with the status line.

The status line extends vertically along the current date line. The status line bulges to the left or right according to each task row's status date. Thus, the status line is a visual indicator of ahead/behind status.

In the first task row below, the status line extends to the left of the current date line, indicating a task which is behind schedule. The second task is on schedule to the current date. The third task is ahead of schedule. 

 

Access this setting under Format | Dates | Current Date | Status Line Properties.