Graph on Schedule


This Import Wizard choice produces:

All columns are from Microsoft Project (no Milestones calculations on this chart).
 
Left Columns -1) Percent Complete,  2) Task Name
 
Right Columns - 1) Baseline Cost (from Project), 2) ACWP from Project, 3) BCWP from Project, 4) BCWS from project, 5) EAC from Project

Graph: Baseline Cost, EV, PV and AC from Project.  EV is BCWP and PV is BCWS.  Values are TimeScaled.  On the first screen of the wizard, the user can choose how much granularity to use (daily, weekly, monthly, quarterly).


Download This Schedule
Download Choices:     Milestones Professional       Milestones Project Companion       PDF

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 