Graph Below Schedule


This Import Wizard choice produces:

All columns are from Microsoft Project (no Milestones calculations on this chart).
 
Left Columns - 1) Task Name, 2) Percent Complete, 3) Baseline Finish
 
Right Columns - 1) BCWS (from Project), 2) BCWP from Project, 3) ACWP from Project, 4) EAC from project, 5) Baseline Cost from Project

Graph: EV is BCWP from Project and PV is BCWS from Project.  Values are TimeScaled.  On the first screen of the wizard, the user can choose how much granularity to use (daily, weekly, monthly, quarterly).